Trade Show Exhibitor Manuals: What Booth Builders Must Submit

Events

Every trade show comes with an exhibitor manual, and the venue’s own rules sit underneath it. World Trade Center Metro Manila publishes its rules in a digital organizer’s kit, and they’re a good map of what a booth builder has to submit, and by when.

Whose rules does a booth have to follow?

Three sets: the venue’s, the show organizer’s, and the official contractor’s. At WTC Metro Manila the venue sits on top. Its Rules and Regulations say the show’s exhibitor manual “must be submitted to WTCMM for approval before final printing and distribution to participants”.

The venue also controls who can build. Only booth contractors and freight forwarders “accredited by WTCMM are allowed to render services at its premises”, and booth questions go through the organizer’s official contractor. Ask your builder for its accreditation before you sign.

What has to be submitted, and when?

Earlier than most briefs assume. Construction drawings and plans go to the venue six weeks before ingress for evaluation and approval. A custom booth needs its specifications “submitted to the official contractor for review, and for approval by WTCMM at least 30 days before the hiring date”.

Height brings more paperwork. Structures over 3.5 meters, and double decks, need “plans and specifications duly signed by a registered civil or structural engineer”, and “These documents will have to be submitted for evaluation and approval of WTCMM at least 30 days before the start of ingress.” Above that, “No structure exceeding 8.0 meters in height shall be allowed in the exhibition halls unless with the prior written approval of WTCMM.”

What can’t happen on the show floor?

Building from scratch. “Only the assembly of pre-fabricated components is allowed to be done on site”, with the venue’s written approval. The rules also say:

→ No cutting. “No cutting of any construction material is allowed inside the halls.”

→ No power tools. “The use of grinders, sanders and power saws is not allowed inside the halls.”

→ No welding. “No welding activity is allowed inside the halls.”

→ No spray paint. “No spray painting is allowed.”

→ No glue, nails or drilling. “Gluing, nailing or boring of holes on the floors and walls are strictly prohibited.”

So the booth has to leave the workshop finished, in panels that bolt or slot together. Touch-ups are limited to brush or roller.

What about rigging, power and heavy exhibits?

Each needs its own form. Hanging loads from the trusses in Halls A to C is capped: “Only 1,000 kilos of load per truss is allowed and assigned rigging points is to be observed.” Banners, flags and rigged pieces go on a Collateral Installation Permit, which “should be submitted together with the design perspective and material specifications for approval by WTCMM”.

Heavy exhibits need a Heavy Equipment Entry Permit for anything over four tons, and the kit notes that “Halls A-C floor load capacity is 250 lbs./sq. ft.” Power can’t be tapped from the building without the venue’s written permission and supervision, and “All electrical lines crossing open walkways or gangways must be covered”.

A smoke machine needs a fire alarm or sprinkler impairment form, but “Submission of this form does not grant automatic approval to use such effects.”

What does the venue check during the show?

Exits and fire equipment. “Exits doors must be free from any obstructions”, and “All fire hose cabinets should not be obstructed with booths or display materials”. Leave both clear on the floor plan, not just on the day. The fire code side of an event is in our event fire safety guide.

The submission calendar

When What goes to the venue
Six weeks before ingress Construction drawings and plans for approval
30 days before Custom booth specs through the official contractor; engineer-signed plans for structures over 3.5 m or double decks
Two weeks before ingress Collateral Installation Permit for banners, flags and rigging
One week before ingress List of delivery vehicles for gate passes
Before any smoke effect Fire alarm or sprinkler impairment form
Heavy exhibits Heavy Equipment Entry Permit for anything over four tons

Start from the show’s own manual

The venue’s rules are the floor. The organizer’s exhibitor manual can add its own deadlines and forms on top, so work back from whichever date comes first.

General information from WTC Metro Manila’s Rules and Regulations (WOPE02, Rev. 03, 2017) and its Digital Organizer’s Kit, as published on the venue’s site in November 2026. Other venues set their own rules; check the current version for your show.

Who should build your booth?

A team that plans the build backward from the venue’s dates. When you brief an events agency, ask for its submission calendar with the quote, and see our booth design service for how a build is scoped. PUNX is an events agency in Makati: 50-plus people, founded 2023, running activations and events for GCash, Sun Life and JTI.

FAQ

When do booth plans have to be submitted at WTC Metro Manila?

Its rules ask for construction drawings and plans six weeks before ingress, and for custom booth specifications through the official contractor at least 30 days before the hiring date.

How tall can a trade show booth be at WTC Metro Manila?

Up to 8.0 meters, unless the venue approves more in writing. Structures over 3.5 meters, and double decks, need plans signed by a registered civil or structural engineer.

Can a booth be built on site at the venue?

Not from raw materials. At WTC Metro Manila only pre-fabricated components may be assembled on site, with written approval, and cutting, power tools, welding and spray painting are not allowed in the halls.

How much weight can be rigged from the ceiling?

WTC Metro Manila allows 1,000 kilos per truss at assigned rigging points in Halls A to C, with a Collateral Installation Permit submitted with the design and material specifications.

Related

Booth designs — how PUNX scopes a booth build
Temporary event structures — the Building Code side of stages and tents
Venue ocular inspection — what to check on the walk-through